Contract value £835,000
Contract duration 44 weeks
The design, build and construction of a new steel framed sports hall, together with a two storey ancillary accommodation block.
Due to the clients wishes, phase I of the project included the completion of the structure and finishes to the sports hall only. Completion of the finishes to the accommodation block was to be carried out as phase II, at a later date.
The works consisted of the completion of the fit out of the accommodation block, as phase 2 of the project. Briefly
lift installation
storage area
kitchen
showers/wc cubicles
wall and floor tiling
suspended ceilings
painting and decorating
completion of car parking and landscaping